Phase 0 milestone 0.9: docs + acceptance
- README rewritten: Docker and native quickstarts, try-it flow, gate
  commands, promote-a-stub steps.
- CONTRIBUTING rules 9-13 (pii_read on PII reads, __audit_redact__ for
  encrypted columns, retention policy per table, models.py registry,
  vendored-code change discipline); PR checklist updated.
- docs/nist-mapping.md: per-control file:line evidence and remaining gap.
- NIST_800_53_CONTROL_MAPPING.md v0.3: Phase 0 notes on 28 rows
  (12 implemented, 12 partial, 4 progress notes on hybrid/tailored rows)
  plus a status-shift table.
- PHASE0_PLAN: 0.9 complete; Definition of Done 12/14 checked with how
  each was verified. Open: first green Gitea CI run, Docker/Postgres boot.
- POA&M and status handoff updated; status TL;DR no longer claims an
  unverified Docker boot.

Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
2026-10-01 14:37:40 -04:00

25 KiB
Raw Permalink Blame History

Plan of Action and Milestones (POA&M)

Youth Program Management System (YPMS)

Document Version: 0.1 (initial seed) Date: 2026-09-30 NIST Reference: SP 800-53 Rev. 5 control CA-5 Status: Pre-Development / Pre-Authorization Companion docs: SYSTEM_SECURITY_PLAN.md, NIST_800_53_CONTROL_MAPPING.md

Drafting note. This POA&M is seeded from three sources: (1) the four SSP tailorings above the RFP-derived requirement floor, (2) the six open policy decisions awaiting AO / OYP / Privacy Officer disposition, and (3) the standard pre-ATO deliverables not yet authored or executed (companion docs, data-sharing agreements, foundational build activities, independent assessments). Because YPMS is pre-development — this is an in-house build following the DCYWP / OWC / Employer 360 pattern, and no code exists yet — there are no vulnerability findings to import. Once initial code lands, findings from SAST/DAST/pentest will be added by ID. Items marked [TBD] for owner or target date are pending assignment by DOES leadership.


Table of Contents

  1. Status Legend
  2. Severity Definitions
  3. Open Items
  4. Closed Items
  5. Maintenance and Reporting Cadence

1. Status Legend

Symbol Meaning
🔴 Open — work not yet started
🟡 In progress — work underway
🟢 Closed — completed and verified
🔵 Risk accepted — formally accepted by AO with documented rationale
⚪ Deferred — known and tracked, scheduled for a later cycle
❓ Awaiting decision — blocked on AO / OYP / Privacy Officer determination

2. Severity Definitions

Severity ratings align with FedRAMP Continuous Monitoring guidance and the DCYWP POA&M scale for consistency across DOES ATO packages.

Severity Definition Default Remediation Window
Critical Vulnerability allows direct unauthorized access to PII or system control, or blocks ATO decision entirely 30 days
High Significant risk to confidentiality, integrity, or availability with credible exploit path; or an ATO artifact that must exist before AO can sign 90 days
Moderate Material weakness without immediate exploit; defense-in-depth gap; or a companion doc/process needed for continuous monitoring 180 days
Low Hygiene; best practice; no immediate exploit 365 days or next major release

3. Open Items

3.1 Critical

ID Severity Title Source Owner Milestones Target Date Status
YPMS-POAM-001 Critical FIPS 199 categorization memo signed by AO NIST RA-2 / SSP §2 Chris Tonjes (System Owner / AO) M1: draft memo — 14 days. M2: Privacy Officer review — 30 days. M3: AO signature — 45 days. 2026-11-15 🔴 Open
YPMS-POAM-002 Critical AO designated in writing for YPMS NIST CA-6 DOES CIO ✅ Closed 2026-09-30: Chris Tonjes designated as AO alongside System Owner and ISSO roles; role concentration accepted and recorded in SSP §5. 2026-09-30 🟢 Closed

3.2 High (open)

Missing ATO artifacts (all must exist before AO signature)

ID Severity Title Source Owner Milestones Target Date Status
YPMS-POAM-010 High System Security Plan finalized and approved NIST PL-2 DOES CIO + ISSO v0.3 exists (ypms/SYSTEM_SECURITY_PLAN.md) in in-house build framing. M1: ISSO review — 60 days. M2: AO signature — 90 days. 2026-12-31 🟡 In Progress
YPMS-POAM-011 High Privacy Impact Assessment authored, reviewed, approved NIST PT-2 Privacy Officer + DOES CIO v0.1 draft complete 2026-09-30 (ypms/PRIVACY_IMPACT_ASSESSMENT.md). M1: Privacy Officer + OGC review — 30 days. M2: AO signature — 60 days. 2026-11-30 🟡 In Progress
YPMS-POAM-012 High Incident Response Plan finalized; tabletop run NIST IR-3 / IR-8 DOES CIO + DC OCTO CISO liaison M1: draft — 30 days. M2: tabletop with OCTO SOC — 60 days. M3: signatures — 90 days. 2027-01-15 🔴 Open
YPMS-POAM-013 High Contingency Plan finalized; functional restore drill NIST CP-2 / CP-4 DOES CIO + OIT Ops M1: draft — 30 days. M2: signatures — 60 days. M3: functional restore drill — 120 days. Recovery envelope: 99.5% SLA / peak-season hard deadlines. 2027-02-15 🔴 Open
YPMS-POAM-014 High Rules of Behavior authored (staff / host / youth+parent variants) NIST PL-4 DOES HR + Privacy Officer M1: staff variant — 30 days. M2: host variant — 60 days. M3: youth/parent variant with parental-consent flow — 90 days. M4: incorporated into onboarding + account-creation workflow — 120 days. 2027-02-01 🔴 Open
YPMS-POAM-015 High NIST 800-53 control mapping finalized NIST PL-2 / CA-2 DOES CIO + ISSO v0.2 exists (ypms/NIST_800_53_CONTROL_MAPPING.md) in in-house build framing (DOES OIT tags, repo/pipeline evidence). M1: ISSO review — 60 days. M2: refresh to v0.3 once architecture and initial code land. 2027-02-28 🟡 In Progress

Data-sharing agreements (blocking on integration builds)

ID Severity Title Source Owner Milestones Target Date Status
YPMS-POAM-020 High DOES–OSSE data-sharing agreement (FERPA) — renewal / scope amendment NIST CA-3 / SA-9; FERPA DOES OGC + Privacy Officer + OSSE liaison M1: pull existing agreement + confirm expiration — 14 days. M2: draft renewal or YPMS-scope amendment — 45 days. M3: OSSE review — 75 days. M4: signature — 105 days. Blocks OSSE school-enrollment ingest build. 2027-01-15 🔴 Open
YPMS-POAM-021 High DOES–CFSA MOU (foster/ward indicator) — renewal / scope amendment NIST CA-3 / SA-9; DC Code Title 4 DOES OGC + CFSA liaison M1: pull existing MOU + confirm expiration — 14 days. M2: draft renewal or YPMS-scope amendment — 45 days. M3: CFSA review — 75 days. M4: signature — 105 days. Blocks CFSA ingest build. 2027-01-15 🔴 Open
YPMS-POAM-022 High SSA Electronic Information Exchange agreement (SSN cross-match) — renewal / scope amendment NIST CA-3; SSA EIES requirements DOES OGC + SSA regional liaison M1: pull existing agreement + confirm YPMS scope coverage — 30 days. M2: amendment drafted if scope is new — 60 days. M3: SSA signature — 150 days (SSA cycle is slow). Blocks SSN verification build. 2027-03-01 🔴 Open
YPMS-POAM-023 High Payroll-vendor selection and security review NIST SA-9 / CA-3 DOES CIO + OYP + Procurement M1: vendor requirements — 30 days. M2: SIG-Lite / SOC 2 collection from candidates — 60 days. M3: selection — 90 days. M4: ISA / DPA signature — 120 days. Blocks payroll integration build. 2027-01-31 🔴 Open

SSP tailorings above the RFP-derived requirement floor

These four items are the tailorings recorded in the SSP Appendix D and control-mapping §5. Building to the RFP wording alone would fail the Moderate baseline.

ID Severity Title Source Owner Milestones Target Date Status
YPMS-POAM-030 High MFA required for all privileged and staff accounts NIST IA-2(1)/(2) — SSP tailoring above C.5.7.6 DOES CIO M1: MFA modality decision (Entra ID conditional access preferred, aligned with OWC/Employer 360) — 30 days. M2: implementation in non-prod — 90 days. M3: production enforcement — 120 days. 2027-02-15 🔴 Open
YPMS-POAM-031 High TLS 1.2+ (target 1.3), FIPS-approved cipher suites; SSL retired NIST SC-8 / AC-17(2) — SSP tailoring above C.5.6.15 DOES CIO M1: TLS baseline in architecture doc — 30 days. M2: enforced in all environments — 60 days. M3: SSL Labs A+ or equivalent on public endpoints — 90 days. 2027-01-31 🔴 Open
YPMS-POAM-032 High FIPS 140-3 cryptography (140-2 acceptable during deprecation window) NIST IA-7 / SC-12 / SC-13 — SSP tailoring above C.5.7.9 DOES CIO M1: crypto library inventory + FIPS mode confirmed for each — 30 days. M2: Key Vault (Azure Gov HSM) provisioned — 60 days. M3: all keys managed via Key Vault — 120 days. 2027-02-28 🔴 Open
YPMS-POAM-033 High IAL2-equivalent identity proofing before youth banking/payroll actions NIST IA-12 — SSP tailoring (RFP silent); links to open decision YPMS-POAM-050 DOES CIO + Privacy Officer + OYP M1: identity-model decision (see YPMS-POAM-050) — 45 days. M2: proofing vendor selection (Login.gov / SSA / DMV records) — 90 days. M3: proofing flow implemented — 180 days. Blocks payroll enrollment for minors. 2027-04-01 ❓ Blocked on YPMS-POAM-050

Foundational build activities

ID Severity Title Source Owner Milestones Target Date Status
YPMS-POAM-040 High Architecture & tech-stack decision recorded NIST PL-8 / SA-3 DOES CIO ✅ Stack decision closed 2026-09-30: Python 3.12 / FastAPI / SQLAlchemy / Postgres on Azure Government (OWC alignment). ✅ Architecture document v0.1 drafted 2026-09-30 (ypms/ARCHITECTURE.md). ✅ Phase 0 plan drafted 2026-09-30 (ypms/PHASE0_PLAN.md). M1: DC OCTO security architecture review — 45 days. 2026-11-15 🟡 In Progress
YPMS-POAM-041 High Azure Government tenant + non-prod environments provisioned NIST CM-2 / CM-6 DOES CIO + DC OCTO M1: subscription request — 30 days. M2: dev + test environments — 60 days. M3: CIS Azure Foundations baseline applied — 90 days. 2027-01-15 🔴 Open
YPMS-POAM-042 High CI/CD pipeline with SAST, SCA, secret scanning, SBOM NIST SA-11 / SR-3 / SR-11 / CM-8 DOES CIO M1: pipeline scaffold — 30 days. M2: SAST + SCA gates — 60 days. M3: SBOM generation per release (CycloneDX) — 90 days. 2026-10-01: M1–M3 implemented in .gitea/workflows/ci.yml (SBOM per CI run); open until the first green run on main (needs a Gitea runner). 2027-01-31 🟡 In progress
YPMS-POAM-043 High Sentinel integration (DOES OIT ships application + Azure resource logs to DC OCTO Sentinel) NIST AU-6 / SI-4 DOES CIO + DC OCTO CISO M1: log-schema agreement with OCTO SOC — 30 days. M2: Sentinel workspace and ingestion — 60 days. M3: correlation rules and alert playbooks — 120 days. 2027-02-28 🔴 Open
YPMS-POAM-044 High Backup + restore procedure documented and tested NIST CP-9 / CP-9(1) DOES CIO + OIT Ops M1: procedure documented — 30 days. M2: initial restore drill — 60 days. M3: annual drill cadence established — 90 days. 2027-02-15 🔴 Open

3.3 Moderate (open)

Open policy decisions (mirrored to SSP Appendix D)

ID Severity Title Source Owner Milestones Target Date Status
YPMS-POAM-050 Moderate Identity model for minors (social-media login vs. IAL2 proofing gates) SSP §17.D DOES CIO + Privacy Officer + OYP + AO M1: options memo (browse-only social, IAL2 for payroll, parental co-auth for under-18) — 30 days. M2: AO decision — 60 days. Feeds YPMS-POAM-033. 2026-11-30 ❓ Awaiting decision
YPMS-POAM-051 Moderate Clarify "Level 3 security" wording from source RFP C.5.7.24 SSP §17.A DOES CIO + ISSO M1: options memo — 30 days. M2: AO clarification memo — 45 days. Treat as NIST 800-63 IAL3/AAL3 pending decision (higher of plausible readings). 2026-11-15 ❓ Awaiting decision
YPMS-POAM-052 Moderate PCI DSS applicability determination SSP §17.E DOES CIO + OYP + OGC M1: transaction-flow review confirming ACH-only via payroll vendor (no card processing in YPMS) — 30 days. M2: PCI scope memo (expected: out of scope) — 45 days. 2026-11-15 ❓ Awaiting decision
YPMS-POAM-053 Moderate Dormant emergency health-record CSV path — in-boundary vs. emergency extension SSP §17.H Privacy Officer + DOES CIO + AO M1: options memo — 30 days. M2: AO decision — 60 days. Recommended: separate emergency-scoped extension with its own PIA addendum. 2026-11-30 ❓ Awaiting decision
YPMS-POAM-054 Moderate Retention policy for audit logs, case records, backups SSP §17.G DOES Records Officer + Privacy Officer + DOES CIO M1: records-schedule review — 30 days. M2: retention policy signed — 60 days. Feeds AU-11 and SI-12 implementation. 2026-12-15 ❓ Awaiting decision

Assessment and pre-launch validation

ID Severity Title Source Owner Milestones Target Date Status
YPMS-POAM-060 Moderate Independent Control Assessment (SCA) commissioned NIST CA-2 / CA-2(1) DOES CIO M1: assessor selection — 60 days. M2: engagement — 120 days. M3: report — pre-Go-Live. 2027-06-30 🔴 Open
YPMS-POAM-061 Moderate Penetration test (external + authenticated) NIST CA-8 DOES CIO M1: scope of work — 60 days. M2: engagement — 120 days. M3: report + remediation POA&M items — pre-Go-Live. 2027-06-30 🔴 Open
YPMS-POAM-062 Moderate Vulnerability scanning cadence in production NIST RA-5 DOES CIO M1: scanner selection — 45 days. M2: monthly authenticated + unauthenticated scans — 90 days. 2027-03-15 🔴 Open

Access control and hygiene

ID Severity Title Source Owner Milestones Target Date Status
YPMS-POAM-070 Moderate System-use notification banner on all authenticated entry points NIST AC-8 DOES CIO + Legal M1: banner text approved — 30 days. M2: implementation — 60 days. 2027-01-31 🔴 Open
YPMS-POAM-071 Moderate Auto-disable inactive accounts (staff 90d, youth 180d — pending records policy) NIST AC-2(3) DOES CIO M1: policy — 45 days (depends on YPMS-POAM-054). M2: implementation — 90 days. 2027-03-15 🔴 Open
YPMS-POAM-072 Moderate Quarterly privileged-access recertification process NIST AC-2 / AC-6(7) DOES ISSO M1: process document — 30 days. M2: first recertification cycle — 90 days. 2027-02-15 🔴 Open
YPMS-POAM-073 Moderate Annual all-user access recertification process NIST AC-2 DOES ISSO M1: process document — 60 days. M2: tooling — 120 days. 2027-03-31 🔴 Open
YPMS-POAM-074 Moderate Continuous Monitoring Strategy document NIST CA-7 / SP 800-137 DOES ISSO M1: draft — 60 days. M2: signatures — 90 days. Codifies cadence table from SSP §15. 2027-02-28 🔴 Open

Data-handling and privacy

ID Severity Title Source Owner Milestones Target Date Status
YPMS-POAM-080 Moderate SSN masking/anonymization design and enforcement NIST SC-28 / SI-10; C.5.7.50 DOES CIO M1: display-layer masking design — 30 days. M2: at-rest encryption confirmed — 60 days. M3: audit — pre-Go-Live. 2027-04-30 🔴 Open
YPMS-POAM-081 Moderate Language Access Act compliance (notices, portal content) DC Language Access Act 2004 DOES CIO + OYP M1: language matrix — 30 days. M2: translated content pipeline — 120 days. 2027-03-31 🔴 Open
YPMS-POAM-082 Moderate Section 508 / WCAG 2.1 AA compliance audit Section 508 DOES CIO M1: automated audit in CI — 60 days. M2: manual audit — 120 days. M3: remediation — pre-Go-Live. 2027-05-31 🔴 Open
YPMS-POAM-083 Moderate Parental consent workflow for under-18 registrants NIST PT-4 Privacy Officer + DOES CIO + OGC M1: consent-flow design — 45 days. M2: implementation — 120 days. 2027-04-15 🔴 Open
YPMS-POAM-084 Moderate Data flow inventory + diagrams (all integrations) NIST CA-3 / CA-9 DOES CIO M1: inventory — 45 days. M2: diagrams — 90 days. Continuously updated. 2027-02-28 🔴 Open

DOES organizational / process

ID Severity Title Source Owner Milestones Target Date Status
YPMS-POAM-090 Moderate ISSO assigned in writing for YPMS NIST PM-2 DOES CIO ✅ Closed 2026-09-30: Chris Tonjes designated as ISSO alongside System Owner and AO roles; role concentration accepted and recorded in SSP §5. 2026-09-30 🟢 Closed
YPMS-POAM-091 Moderate Role-based training curriculum (OYP staff, eligibility examiners, payroll admins) NIST AT-3 DOES ISSO + OYP M1: curriculum outline — 60 days. M2: content — 120 days. M3: first delivery — pre-Go-Live. 2027-05-31 🔴 Open
YPMS-POAM-092 Moderate Personnel background-check confirmation for all YPMS-access personnel NIST PS-3 DOES HR + DC OCTO M1: current DOES/OIT team background-check status verified — 30 days. M2: gaps closed — 90 days. 2027-01-31 🔴 Open
YPMS-POAM-093 Moderate Change Management Plan NIST CM-3 / CM-9 DOES CIO + OIT Ops M1: draft — 45 days. M2: DOES + OCTO NOC review — 90 days. 2027-02-15 🔴 Open
YPMS-POAM-094 Moderate SORN applicability determination NIST PT-6 Privacy Officer + OGC M1: applicability memo — 60 days. 2026-12-31 ❓ Awaiting decision

3.4 Low (open)

ID Severity Title Source Owner Milestones Target Date Status
YPMS-POAM-100 Low Approved-software list maintained and reviewed NIST CM-10 DOES CIO Quarterly review starting after first release. Ongoing 🔴 Open
YPMS-POAM-101 Low Anti-bot / rate-limit measures on public MBSYEP peak windows NIST SC-5 DOES CIO M1: threat model — 60 days. M2: WAF rules — 90 days. Tuned for summer peak. 2027-04-30 🔴 Open
YPMS-POAM-102 Low FOIA response workflow with PII redaction guidance DC FOIA DOES OGC + Records Officer M1: workflow document — 90 days. 2027-03-31 🔴 Open
YPMS-POAM-103 Low Emerging-tech (GenAI/ML) governance if enabled NIST SA-9 / SR-3 DOES CIO + Privacy Officer Only triggers if GenAI features added. Deferred pending scope decision. Deferred ⚪ Deferred
YPMS-POAM-104 Low Vendor lock-in and data-portability provisions in payroll/LMS contracts NIST SA-4 DOES OGC + Procurement Included as clauses during vendor selection. 2027-01-31 🔴 Open
YPMS-POAM-105 Low Legacy data-migration plan (7 tools: PF3, TMS, MicroStrategy, Host/Participant App, Scanning, Transfer, manual payroll) NIST SI-12 DOES CIO + OYP + OIT M1: source inventories — 90 days. M2: mapping and transform design — 180 days. M3: cutover strategy — pre-Go-Live. 2027-05-31 🔴 Open
YPMS-POAM-106 Low Legacy system decommission schedule and destruction evidence NIST MP-6 / SR-3 DOES CIO + OIT Follows successful cutover. Post-Go-Live ⚪ Deferred

4. Closed Items

Closures retained for traceability.

ID Title Closure Date Verification / Evidence
YPMS-POAM-002 AO designated in writing for YPMS 2026-09-30 Chris Tonjes (DOES CIO) designated as AO. Role-concentration risk accepted per SSP §5. Update SSP §3.2 reflects the designation.
YPMS-POAM-090 ISSO assigned in writing for YPMS 2026-09-30 Chris Tonjes designated as ISSO. Role-concentration risk accepted per SSP §5. Update SSP §4 reflects the designation.
— Stack decision (partial closure of YPMS-POAM-040) 2026-09-30 Python 3.12 / FastAPI / SQLAlchemy / Postgres selected (OWC alignment).
— Architecture document v0.1 (partial closure of YPMS-POAM-040) 2026-09-30 ypms/ARCHITECTURE.md drafted; forward-looking design following the OWC pattern.
— Phase 0 plan v0.1 (partial closure of YPMS-POAM-040) 2026-09-30 ypms/PHASE0_PLAN.md drafted: framework vendor-in, auth, RBAC, audit, Registrant vertical slice, 501 stubs on remaining ARCH §6.1 entities.
— Phase 0 milestone 0.1 shipped (partial closure of YPMS-POAM-040) 2026-09-30 Repo scaffold, Docker Compose, FastAPI factory with /healthz + /readyz, structlog + request-id middleware, Alembic baseline, CI workflow, README + CONTRIBUTING. Tests green (3 passing, ruff + mypy clean). Committed as 393631a.
— Phase 0 milestone 0.2 shipped (partial closure of YPMS-POAM-040) 2026-09-30 OWC framework vendored (base/crud/bulk/pagination/router/version_history + audit + security/rbac + users + auth stub) with owc→ypms renames. YPMS pii_audit decorator added. Pagination bug in upstream OWC fixed here (peek-ahead cursor). 26 tests passing, 93.10% coverage. Migration 0002 creates the framework tables.
— Phase 0 milestone 0.3 shipped (partial closure of YPMS-POAM-040) 2026-09-30 Local password auth + JWT access/refresh tokens with YPMS-specific claims (uid, roles, iam.assurance_level, mfa_verified). Endpoints: /auth/login, /auth/refresh, /auth/me, /auth/change-password. NIST AC-7 lockout at 5 attempts / 15 min (source RFP C.5.7.10). 43 tests passing, 93.47% coverage.
— Phase 0 milestone 0.4 shipped (partial closure of YPMS-POAM-040) 2026-09-30 Data-driven RBAC seed: 8 roles + permissions matrix (30 entities × 8 actions) at src/ypms/seed/. Bootstrap admin auto-seeded (chris / DOES_SYSTEM_ADMIN). Loader idempotent + validates cell references. python -m ypms.seed.run chained into docker-compose. 53 tests passing, 92.20% coverage.
— Phase 0 milestone 0.5 shipped (partial closure of YPMS-POAM-040) 2026-09-30 Registrant vertical slice: model, schemas, router, migration 0003. SSN app-layer encrypted (AES-256-GCM, column-bound AAD) and masked in the serializer (C.5.7.50 / SC-28). pii_read audit on every read path (C.5.6.9 #5 / AU-14). Audit + version-history snapshots redact ciphertext via __audit_redact__. Portal-only roles limited to own row. 98 tests passing, 94.83% coverage. Evidence trace at docs/coverage/registrant.md.
— Phase 0 milestone 0.6 shipped (partial closure of YPMS-POAM-040) 2026-09-30 501-stub routers for 26 entities; every route enforces RBAC and writes an audit row before returning 501 (source RFP C.5.7.27; NIST AC-3, AU-12). Matrix-driven test sweep covers every entity × role × action. Permission-matrix review items recorded in PHASE0_STATUS.md. 138 tests passing, 95.05% coverage.
— Phase 0 milestone 0.7 shipped (partial closure of YPMS-POAM-040) 2026-10-01 Retention scaffold (NIST AU-11, SI-12; source RFP C.5.7.42): every table carries a policy; PIA §9 interim periods encoded but unapproved; report-only nightly job logs eligible counts and audits each run. Implementation is ready to consume the signed schedule from YPMS-POAM-054 (flip approved, cite authority). 156 tests passing, 95.91% coverage.
— Phase 0 milestone 0.8 pipeline complete (partial closure of YPMS-POAM-040; advances YPMS-POAM-042) 2026-10-01 Gitea Actions workflow with lint, strict types, tests + coverage floor, migration drift test, SAST, SCA on runtime deps, full-history secret scan, CycloneDX SBOM. All gates pass locally; green-on-main pending runner registration. Removed ecdsa (PYSEC-2026-1325) by moving JWT to PyJWT; enforced 32-byte JWT secret (RFC 7518). 158 tests passing, 95.83% coverage.
— Phase 0 milestone 0.9 shipped (partial closure of YPMS-POAM-040) 2026-10-01 Docs + acceptance: README, CONTRIBUTING rules 9–13, docs/nist-mapping.md, control mapping v0.3 with file:line evidence (12 ✅ / 12 🟡). Closed Phase 0 control gaps: failed-login audit (AU-2, C.5.7.39), opaque error handler + hidden SQL parameters (SI-11, C.5.7.43), startup retention-policy check, migration hash pinning (CM-3). End-to-end HTTP verification from a clean clone. Phase 0 exit remaining: Docker/Postgres boot check and first green Gitea CI run. 167 tests passing.

5. Maintenance and Reporting Cadence

Activity Frequency Owner
POA&M review — status update on every open item Monthly DOES ISSO
POA&M report to AO Quarterly DOES CIO
New-finding intake (from scans, assessments, incidents) Continuous DOES ISSO
Milestone-slip escalation to CIO On any 30-day slip past target date DOES ISSO
Closure verification (independent from remediator) Per closure DOES ISSO
POA&M archive at ATO decision At initial ATO and each reauthorization DOES CIO

Reporting format for status update

Each open item gets a one-line status update per monthly cycle, retained in an append-only status log (ypms/POAM_STATUS_LOG.md — to be created on first cycle):

YYYY-MM-DD YPMS-POAM-NNN [🔴|🟡|🟢|🔵|⚪|❓] {status text ≤ 200 chars}

Status text records: what moved, blockers, next milestone due.


End of draft v0.1.